By SolarQuant Editorial. Published 2026-10-05. Last updated 2026-10-05.
Most solar models are built around the term loan. Two small facilities sit beside it: the VAT facility in construction and the working capital facility in operations. Neither changes the size of the senior debt much, but a model that leaves them out can run out of cash.
Refundable VAT must be funded because the project pays it to contractors months before the tax authority pays it back. A project company in construction has no sales, so it has no VAT on sales to set against the VAT it pays. The VAT becomes a claim on the tax authority that turns into cash only when the refund arrives.
A 2001 law firm note on Spain says the project company's VAT can be a substantial amount, so a VAT facility finances it. In our example, 15% VAT on USD 30m of construction contracts is USD 4.5m. That sits on top of the USD 40.0m funding requirement and equals 11% of it.
VAT treatment differs by jurisdiction. An IMF paper on extractive industries says common VAT measures there exempt or zero-rate the goods and services that companies buy.
Other regimes shift the VAT charge to the buyer. Operis notes that under the UK's domestic reverse charge VAT facilities are likely to disappear from financial models. Confirm the rules with a tax adviser before building any of this.
A VAT facility is a short-term loan used only to pay VAT on construction costs, and repaid from the VAT refunds as they arrive. One contract definition describes it as a facility set up solely to bridge the payment of VAT refunds from an official body. It sits outside the term loan and is usually much smaller.
What the term sheet typically says. The facility is drawn with each contractor invoice, for the VAT part only. The same 2001 note says repayment is automatic each time a refund is paid. It describes no repayment schedule, but a final maturity date.
Structures vary. Some VAT facilities are revolving. A 2020 Bracewell note on Saudi Arabian PPPs says VAT there was wrapped in ordinary working capital facilities, with no dedicated VAT facility.
What it changes in the model. The model needs a VAT line in construction costs, a refund line that lags it, and a facility balance between the two. Interest and commitment fees on the facility are a real cost that the sources and uses must cover.
What happens if refunds are late. The final repayment date does not move when the tax authority is slow. Our reading is that any balance left on that date must be repaid from equity, sponsor support or project cash, so read the clause.
Late refunds are a real risk. An IMF paper on extractive industries says refund delays can reach years. It adds that a refund paid in a weaker local currency is worth less in USD.
Refund lag is the time between paying VAT to a contractor and receiving the refund. It sets both the peak balance of the VAT facility and its interest cost, so it belongs on the inputs sheet.
The example. The USD 30m of contracts is invoiced evenly over 12 months, so USD 0.375m of VAT is drawn each month. Each drawing is repaid when its refund arrives. Our assumptions: drawings at the start of each month, a USD 4.5m commitment that falls as it is drawn, and no redrawing.
At the base lag the facility is cleared by month 21, eight months into operations. At 15 months the full limit is used. A balance is still owed at the final repayment date, which we have invented as 12 months after construction ends.
Each drawing is outstanding for exactly the lag, so the interest has a simple form.
At the base lag that is USD 4.5m x 7.5% x 9/12, or USD 0.253m. The commitment fee adds USD 0.025m, for a total of USD 0.28m.
Each extra month of lag adds about USD 28,000 of interest. In the base case USD 0.17m of the interest falls in construction and USD 0.08m after completion, when it must come from operating cash.
The common mistake is to refund VAT in the month it is paid. The facility then never draws, so about USD 0.19m of construction-period cost drops out of the funding requirement. The USD 0.08m of interest after completion, paid from operating cash, is missed too.
A working capital facility is a revolving credit line that pays operating costs while the project waits for customers to pay. It is repaid from revenue as cash comes in, and it can be drawn again up to its limit. The lender charges interest on the drawn part and a commitment fee on the undrawn part.
The cycle repeats every month, so the facility is never drawn for long on any one invoice. Three things drive how much is needed: customer payment days, supplier payment days and seasonal output. A solar plant invoices more in its sunniest months, so the receivable peaks then, not at the annual average.
One modelling guide adds a warning: the first build-up of working capital is a permanent cash need. It says the permanent part should come from core funding, with a revolving facility used for flexibility.
The working capital need is the cash tied up in unpaid customer invoices, less the credit that suppliers give. A first estimate uses payment days.
The example. Receivables are USD 5.6m x 60/365, or USD 0.92m. Payables are USD 1.0m x 30/365, or USD 0.08m. The need is USD 0.84m, which leaves USD 0.16m of headroom under the USD 1.0m limit.
That headroom is thin. If customers pay in 71 days instead of 60, the need reaches the limit. At 90 days it is USD 1.30m, and the last USD 0.30m must come from the project's own cash.
The cost. We assume the facility is half drawn on average, which is an invented utilisation. Interest is USD 0.5m x 7.5%, or USD 37,500, using the 4.0% base rate plus the 3.5% margin. The commitment fee is USD 0.5m x 1.5%, or USD 7,500.
The total is USD 45,000 a year, about 1.1% of year 1 CFADS.
The common mistake is to size the need on annual averages. A monthly model shows the peak, and the peak is what the limit must cover.
Both facilities bridge timing, not a lack of value, but they differ in when they are drawn and what repays them. The sizes and prices below are from the invented example. The other rows are our reading of common practice.
| VAT facility | Working capital facility | |
|---|---|---|
| Purpose | Pays VAT on construction costs until it is refunded | Pays operating costs until customers pay |
| When drawn | Construction, with each contractor invoice | Operations, when costs fall due before receipts |
| Repaid from | VAT refunds | Revenue |
| Redrawable | Usually not, though some are revolving | Yes, up to the limit |
| Tenor | Short: construction plus the expected refund lag, with a final repayment date | Revolving, for the term set in the documents |
| Limit in the example | USD 4.5m | USD 1.0m |
| Price in the example | 7.5% all-in, 1.2% commitment fee | 7.5% all-in, 1.5% commitment fee |
| In or out of gearing | Practice varies, read the definition | Practice varies, read the definition |
Practice varies, and the answer sits in the definitions of each deal, not in a market rule. We found no public source that sets a standard treatment, so this section is our reading. The pillar article, How to read a solar project finance term sheet: a modeller's guide, explains where to find those definitions.
Gearing. The result depends on whether debt means the term loan only or all financial debt. In the example, senior debt of USD 25.1m against USD 40.0m of funding is 62.7%. Adding the USD 4.5m VAT facility to both sides gives 66.4%, and a project already at the 70% cap would show 73.0%.
Cover ratios. Two definitions matter: what counts in CFADS and what counts in debt service. Published guides define CFADS after working capital movements, and one writes the formula with a change in working capital line.
This is an illustration, not the example's result. The series' example assumes no working capital movement inside the USD 4.2m of year 1 CFADS, as stated in "CFADS, DSCR and LLCR defined properly". On the published definition, deducting the USD 0.84m build-up in year 1 would cut CFADS from USD 4.2m to USD 3.36m. With debt service of USD 3.231m, the DSCR would read 1.04x instead of 1.30x, under the 1.10x default level. The 1.04x figure shows what would happen if the one-off build-up were deducted and not funded by the facility. Whether a facility drawing offsets this, and whether facility interest counts as debt service, is set by the documents.
VAT payments, refunds and VAT facility flows are normally kept out of CFADS, in our reading, because they net to zero over time. The related article, The cover ratio ladder, explains how each ratio is tested.
Interest and fees on both facilities are financing costs that usually rank with senior debt costs, but the exact place is deal-specific. One published illustration of the order runs: operating costs, taxes, senior debt service, reserve accounts, subordinated debt, then distributions. The same guide says the exact ordering is deal-specific.
Neither facility appears in that generic list, which is part of why modellers forget them. Our reading of common practice is below.
Model each facility as its own account on a monthly timeline, because both exist to solve timing inside a period. Our example uses annual periods for the term loan, and real deals usually use six-month periods. Neither is fine enough for these two facilities.
Most errors come from treating these facilities as too small to model. The list below is our reading.
A VAT facility is a separate loan from the term loan, with its own limit, price and final repayment date. Whether it shares the senior security and counts in the gearing ratio depends on the documents. In our reading, it is rarely part of the debt that the DSCR sizes.
Yes. Sponsors can pay the VAT with equity and take the refunds back later. In the example that means up to USD 3.4m of extra equity at the base lag, so the choice is a cost comparison.
The VAT becomes a permanent project cost, and the facility must still be repaid on its final repayment date. In the example that is up to USD 4.5m from equity or project cash. Model it as a downside case, not as the base case.
Not always. A project can fund the USD 0.84m need from equity at completion or from retained cash. The facility costs about USD 45,000 a year at our invented utilisation, so compare that with the cost of holding cash.
Sometimes. The Renewables Valuation Institute says a revolving facility in renewable energy can serve as a working capital line, VAT facility or debt service reserve facility. Check the permitted purposes in the term sheet, and model each use against its own limit.
No. The DSRA protects lenders when cash flow falls short of debt service. The working capital facility covers the timing of operating cash, and it must be repaid.
Pages opened on 4 October 2026 and checked again on 5 October 2026. The example project is invented and has no source. Public sources on VAT facilities are thin, so points marked as our reading have no source.