By SolarQuant Editorial. Published 2026-10-10. Last updated 2026-10-10.
When a registry fails, an issuer cannot issue or the scheme rules change, renewable energy certificates may not be delivered. Most templates cited here then excuse the affected delivery without compensation, so the project simply loses that revenue. For a modeller, this means a downside case in which certificate revenue pauses or stops, and a check that the cover ratios survive it.
We use the same invented 40 MWp solar plant as the rest of the series. It sells power under a PPA, keeps its certificates and sells 52,000 of them a year forward in two batches. Every figure below is invented and describes no real project, buyer, issuer or market.
| Item | Example figure (invented) |
|---|---|
| Plant and power sale | 40 MWp, one 20-year USD PPA at USD 80 per MWh for power only |
| Certificates | Kept by the project and sold separately (unbundled), one per MWh of metered net output |
| Year 1 certificates, P90 | 70,000, falling 0.5% a year |
| Certificate price | USD 2.0 per certificate, flat |
| Year 1 net certificate revenue | USD 134,100 (3.19% of CFADS) |
| Forward sale | 52,000 a year for three vintage years, in two batches of 26,000, USD 104,000 a year, USD 312,000 in total |
| Issuance timing | 64 days after each half-year ends |
| Year 1 CFADS (lender's case) | USD 4.2m, falling 0.5% a year |
| Senior debt | USD 25.07m, 7.0%, 12 years, sculpted so debt service = CFADS / 1.30; year 1 debt service USD 3.231m |
| DSCR levels | Sizing 1.30x, lock-up 1.20x, default 1.10x |
| Debt view of certificates | Full credit for net certificate revenue adds USD 0.81m of debt (USD 25.88m); 50% credit adds USD 0.40m |
| Stop case | Debt sized with full credit, certificate revenue stops from year 4: year 4 DSCR 1.26x |
We use annual periods for simplicity; real deals usually test cover every six months.
All four templates cited here define force majeure around an event beyond a party's reasonable control. The I-REC(E) and EFET templates add that it must make delivery or acceptance impossible. Several name registry and issuer failures as examples, but differ on when an issuer's failure counts and whose fault defeats the claim.
The exclusions differ too. The I-REC(E) agreement leaves a blank for exclusions, and its guidance note says that, if unused, "no express exclusions apply". The North American agreement bars force majeure based on the buyer's lost markets or the seller's chance to sell elsewhere at a higher price.
Our reading: where the project is both plant operator and seller, the seller-breach carve-out does most of the work. An issuer that rejects the project's own registration or meter data is unlikely to give it force majeure relief.
The affected quantity is excused for both sides: the seller need not deliver, and the buyer need not accept or pay. Nobody owes compensation for it. The templates differ on whether the obligations are released for good or only paused, and on what a long event allows.
| Template | Effect on the affected quantity | Long-running event |
|---|---|---|
| I-REC(E) Standard Single Trade Agreement | Claiming party relieved to the extent prevented, and the guidance note says its obligations "are not suspended"; the other party's matching obligations are also relieved | After a set period, parties may agree to discharge an affected part; if the whole quantity is affected, the other party may terminate |
| EFET certificates master agreement | Obligations are "released (and not merely suspended)"; the buyer's acceptance and payment obligations are released too | After more than thirty consecutive calendar days, the other party may extend the release or terminate the affected Individual Contracts |
| North American master REC agreement | Obligations "suspended during the continuance of said inability, but for no longer period" | No separate termination right in the force majeure article |
| NYSERDA Agreement for the Sale of Renewable Energy Certificates | Neither party liable for the failure or delay | After more than 45 days, NYSERDA may terminate, owing only delivery of certificates already paid for |
Our reading: release and suspension lead to different models. A released batch is gone from the contract, although certificates issued after the event could still be sold spot. A suspended delivery may only move later in time.
In the example, if registry failure excuses one batch of 26,000 certificates, the project loses USD 52,000 of contract revenue for that half-year. It owes nothing, and is owed nothing.
It covers a change to the certificate scheme's rules, to the law, or to the system itself. The I-REC(E) and EFET templates ask for good-faith renegotiation first, then allow termination with no amount owed if talks fail. The North American master agreement instead keeps most trades alive at the agreed price.
The overlap rules also differ. The I-REC(E) agreement treats an event that is both force majeure and a Change in Applicable Rules as the latter. EFET says a Change in Law is not of itself force majeure, unless it makes performance prohibited or impossible.
Price is negotiable in some templates. The I-REC(E) guidance note says its clause "does not exclude price adjustments". EFET offers an election under which amendments "shall not include any upward or downward adjustments to the Contract Price".
Ask three questions in order: did the seller cause it, is it a rule change, and is it an event beyond control? Only the last two excuse the seller, and they lead to different ends.
The order matters because the I-REC(E) agreement treats an event that fits both definitions as a rule change. In the I-REC(E) agreement, both tests also exclude some failures caused by a party's own breach. A registry outage on a delivery date falls in the third row; a country leaving the system falls in the second.
Yes, in part and for a time. Public notices describe an issuance pause, a suspension of GO exports and a buyer standard that narrowed eligibility.
| Date | Body | Event | Clause it would test (our reading) |
|---|---|---|---|
| 10 November 2023 | Association of Issuing Bodies (AIB) | Board decided not to reinstate the suspension of Icelandic GO exports | None further: the suspension ended |
| 1 June 2023 | AIB | Board conditionally lifted the suspension, pending resolution of a rectification order by its Icelandic member | Release ends; later deliveries resume |
| 27 April 2023 | AIB | Board suspended all exports of Icelandic GOs after a compliance assessment on "double claiming of energy attributes" | Registry or transfer system suspension, or a change in law or scheme rules |
| 12 December 2022 | RE100 | Published technical criteria with a "fifteen-year commissioning or re-powering date limit", assessed on disclosures covering twelve months starting on or after 1 January 2024, with grandfathering for contracts with operational commencement dates before 1 January 2024 | Usually neither clause: certificates still issue, but fewer buyers may value older plants' certificates |
| 16 September 2022 | I-REC Standard Foundation (now the I-TRACK Foundation) | Lifted the pause, having had no feedback from a national authority | Release ends; later deliveries resume |
| 15 August 2022 | I-REC Standard Foundation | Paused I-REC(E) issuance for a select group of devices in Indonesia while it gathered the national authority's requirements | Issuer failure to issue, or an official notice that is a Change in Applicable Rules |
Our reading: a pause that lifts within weeks puts one batch at risk, while a country leaving a system stops certificate revenue. A claims standard change sits outside both clauses and reaches the model through price.
Other claim frameworks, such as GHG Protocol Scope 2, CDP and national reporting, set their own criteria. "What buyers need from renewable energy certificates: Scope 2 quality criteria, market boundaries and vintage" compares them.
They remove certificate revenue without paying anything in return. In the model, that shows up three ways: revenue that pauses, revenue that stops, and a forward sale that ends with no amount owed.
Cover ratios move only if lenders counted certificate revenue when sizing. With full credit, debt rises to USD 25.88m and year 4 debt service is USD 3.286m (invented, derived). With half credit, a stop from year 4 gives 1.28x; with none, cover stays at 1.30x.
A permanent stop costs about 0.04x and leaves 0.06x of headroom above lock-up, because net certificate revenue is only about 3% of CFADS. The invented pause costs about 0.02x, in year 4 only. "Renewable energy certificate revenue in the lender's model: how much counts for debt sizing" covers how much credit lenders give.
Model registry, issuer and rule-change risk as downside cases on top of an unchanged base case. "How to read a renewable energy certificate sale agreement for a solar project: a modeller's guide" places these clauses in the whole agreement.
The I-REC(E) and EFET agreements name a suspension, failure or malfunction of the registry or transfer system as an example. Relief covers only what the outage prevents; the claiming party must notify the other side and use reasonable efforts to overcome or mitigate it. Our reading: an outage that ends before the delivery date excuses nothing.
The I-REC(E) agreement has tick boxes that add an Upstream Party, such as the plant operator, to its breach test for redemption and issuer failures. Its guidance note says this "may be of particular relevance in a chain transaction". EFET lists an issuing body's failure as an example only where the contract names a specific Production Device.
The I-REC(E) agreement names a country's withdrawal from the I-REC system as a Change in Applicable Rules. The parties first try to amend the agreement; if that fails, either may terminate with no liability. Certificates already delivered must still be paid for.
It depends on the template. The I-REC(E) guidance note allows price adjustments in the renegotiation, and EFET lets the parties rule them out by election. The North American master agreement's commentary says trades continue at the agreed price even if the RPS is cancelled.
Under the North American master agreement, the buyer bears it unless the seller represents compliance, and that representation speaks only at the Trade Date. If the trade is Regulatorily Continuing, the seller must deliver product that complies at the Delivery Date, including substitute product acceptable to the buyer if appropriate.
Pages opened and checked on 10 October 2026. The example project is invented and has no source.