Delivery point, metering and grid charges: where title passes and what it does to revenue

By SolarQuant Editorial. Published 2026-10-05. Last updated 2026-10-05.

The delivery point decides whose meter sets revenue, who bears energy lost on the way and who pays for grid connection. Public contracts place it at the plant, at the buyer's substation or at a point on a connecting line, and each choice changes the revenue line in a model. In the example below, a 1.5% loss before the meter lowers year 1 DSCR from 1.30x to 1.27x.

What example does this article use?

The example is an invented 40 MWp ground-mounted solar plant in no named market. One buyer takes the power at the plant substation, which is the delivery point, and pays in USD under a 20-year PPA from the commercial operation date. Construction takes 12 months.

The example is the revenue side of the plant used in the first series. Other delivery points appear below as separate what-if cases on this same plant, never as a second contract.

Item Example figure
Plant 40 MWp, ground-mounted
Delivery point Plant substation
PPA term 20 years from commercial operation
Year 1 generation, P90 70.0 GWh (1,750 kWh per kWp)
Degradation 0.5% a year
Tariff USD 80 per MWh, flat
Year 1 revenue, lender's case USD 5.6m
Year 1 operating costs USD 1.0m
Year 1 tax USD 0.4m
Year 1 CFADS USD 4.2m
Year 1 debt service USD 3.231m
Funding requirement USD 40.0m
Senior debt, 12 years, 7.0% all-in USD 25.1m (62.7% gearing)
Equity USD 14.9m
DSCR levels Sizing 1.30x, lock-up 1.20x, default 1.10x

Debt service is sculpted so that it equals CFADS divided by 1.30. We use annual periods for simplicity. Real deals usually use six-month periods.

What is the delivery point, and what passes there?

The delivery point is the place where the seller hands over the power to the buyer. In public contracts, title and risk of loss pass at that point.

The point is usually named by its place on a single-line diagram. Three placements appear in the public documents we opened.

Title and risk pass at the delivery point, here the plant substation
Figure 1. single-line diagram, invented example · 1 plant, 3 candidate delivery points

In the example the delivery point is the plant substation (point B). Points A and C are what-if placements on the same plant. They show how a different point moves the equipment and the losses between seller and buyer.

Where the delivery point sits What the contract text says Source
High voltage side of the generator step-up transformer Title and risk of loss pass there. Losses before the point are the seller's and losses beyond it are the buyer's. World Bank sample PPA, Vietnam
Point where the seller's facilities connect with the buyer's facilities Title and risk of loss pass there. The seller carries line losses from that point to the interconnection point. Standard contract, California, USA
A point shown in a schedule to the contract Title and risk of loss pass to the purchaser there. SEIA C&I PPA v2.0, USA
Point where output is delivered to the buyer's grid, at high voltage transformer bay terminals Defined as the point of connection where the energy output is delivered to the grid. Standard PV PPA, Jordan
11 kV side of a 33/11 kV substation of the buyer The seller bears the charges and losses of transmission from the project up to that point. Standard PPA, Maharashtra, India

Placements differ, so the model starts from the contract's own definition of the point. Where the point is at the buyer's substation, the connecting line and its losses sit on the seller side. Not every public contract says where title passes, so the model should not assume a clause the contract lacks.

How is the energy metered, and how are meter disputes settled?

The revenue meter is the device whose reading becomes the invoice. Contracts say who supplies and owns it, what backs it up, how often it is tested and who decides when readings disagree.

The public documents we opened show several designs. They are separate variants and no single contract uses all of them.

Topic Variant seen in a public document Source
Who owns the main meter The seller's own revenue grade meter, built to a named accuracy standard. The buyer may add its own meter at the same location. SEIA C&I PPA v2.0, USA
Who owns the main meter Meters are procured by the purchaser, installed and tested by the seller, then owned and maintained by the purchaser. The seller keeps a back-up system. Energy purchase agreement, Pakistan
Who pays for meters The seller bears the cost of installation, testing, calibration, maintenance, renewal and repair of meters on its side of the delivery point. Standard PPA, Maharashtra, India
Who pays for meters Equipment cost normally falls on the buyer. A common practice is that the supplier buys, installs and runs the meters and the user covers its costs. PPA guide, Mexico
Check meter The project company installs main and check metering equipment at its own expense. Standard PV PPA, Jordan
Test and recalibration The buyer tests and recalibrates the check meter at least once every contract year. A deviation above 0.3% against the main meter triggers a meter check or recertification. Standard contract, California, USA
Test and recalibration A discrepancy above 2% over a contract year lets the purchaser ask the seller to calibrate the meter at the purchaser's cost. SEIA C&I PPA v2.0, USA
Meter fails or reads wrongly Energy for the period is taken from the check meter. If there is none, the parties agree the quantity or treat it as a dispute. Standard PV PPA, Jordan
Who settles a dispute Metering disputes that the parties cannot resolve go to an expert. Standard PV PPA, Jordan

The 0.3% and 2% figures are the triggers in those two templates. They are not revenue adjustments and they are not market norms.

In the model, the meter sets billed energy, so any gap between plant output and metered output is revenue the plant never invoices. A failed meter also moves cash in time, because replaced readings may be agreed after the invoice date. Our reading is that a modeller should test a year of under-read energy rather than assume a perfect meter.

Who pays for energy lost before the delivery point?

Energy lost between the generator and the delivery point is normally the seller's loss, because the meter sees only what arrives. Public contracts state this in three ways.

In the model, the yield study and the invoice must be measured at the same place. Our reading is that a P90 figure taken at the inverter output overstates billed energy when the meter sits further down the line. The model then needs a loss factor from the plant to the meter, with the factor taken from the yield study or grid study.

Energy that the grid cannot take is a separate case. It is covered in Take or pay and deemed energy in a solar PPA: who pays when the power is not taken.

Who pays for interconnection and grid charges?

Interconnection cost is the cost of the equipment and approvals that join the plant to the grid. Grid charges are the recurring network fees for moving power across it. Public documents split both between seller and buyer in different ways.

Cost Variant seen in a public document Source
Interconnection works and upgrades The seller carries interconnection costs, including necessary facility upgrades, and obtains and maintains the interconnection rights and agreements at its sole cost. Standard contract, California, USA
Interconnection works Each party builds the facilities on its own side of the interconnection point. Energy purchase agreement, Pakistan
Interconnection works The buyer designs, builds, owns and runs the interconnection facilities at its expense, by a date set in the contract. Standard PV PPA, Jordan
Transmission charges to the delivery point The seller bears all transmission charges and losses from the project up to the delivery point. Standard PPA, Maharashtra, India
Network charges, off-site buyer Network costs still apply in a merchant PPA. A private wire arrangement is exempt from network costs because the project does not use the public network. Briefing note, Regen, UK
Grid access charges, off-site buyer In Spain a corporate consumer must contract with the network distribution company and pay the grid access charges needed to take the power. Corporate PPAs, Bird & Bird

The model treats the two cost types differently. A one-off works cost paid by the seller adds to the funding requirement and so to equity. A recurring charge paid by the seller lowers CFADS in every year.

Our reading is that where the buyer builds the connection, its completion date also sets the earliest date the plant can deliver. That link is covered in The commercial operation date, longstop dates and delay damages.

How much do delivery point terms move revenue and DSCR?

A loss or charge that sits on the seller's side of the delivery point comes straight off year 1 CFADS. In the example, each case below moves DSCR by a few hundredths and none reaches the lock-up level.

All cases are invented what-ifs on the example plant. Each holds costs and tax at the base case, which is a simplification, and uses year 1 P90 energy of 70,000 MWh against debt service of USD 3.231m.

Loss and grid charge together cut year 1 DSCR to 1.23x, above lock-up
Figure 2. invented what-if cases on the example plant · year 1 P90, debt service USD 3.231m

Each seller-side item lowers DSCR a little. Together the loss and the charge take 0.07x off the 1.30x sizing level and leave 0.03x before lock-up.

Case (invented) Input Year 1 effect Year 1 CFADS
Base case None None USD 4.200m
Meter reads low Meter reads 0.5% below true output for the year 0.35 GWh not billed, revenue down USD 0.028m USD 4.172m
Loss before the point 1.5% of output lost on a seller line to a buyer substation 1.05 GWh not billed, revenue down USD 0.084m USD 4.116m
Grid charge Seller pays USD 2.0 per MWh delivered USD 0.140m of added cost USD 4.060m
Loss and charge together The two cases above combined USD 0.224m less cash USD 3.976m
Seller-funded connection works USD 1.2m of works paid by the seller Funding requirement USD 41.2m. Debt stays USD 25.1m, so equity rises from USD 14.9m to USD 16.1m. USD 4.200m

If the loss and the charge lasted for the whole debt life and scaled with output, DSCR-sized debt would fall by about USD 1.3m, from USD 25.1m to USD 23.7m. About 4.0 GWh a year, or 5.8% of year 1 P90 output, would have to go unbilled to bring DSCR down to the 1.20x lock-up level.

How do you model delivery point, metering and grid charges?

The model turns the contract's delivery point into a billed energy line, a loss line and a cost line. These steps follow the order of the revenue build.

  1. Mark the delivery point from the contract on a single-line diagram of the plant. Note every item of equipment and every line between the generator and that point.
  2. Record who owns the revenue meter, what backs it up and which tests the contract requires. Record where title and risk pass only if the contract states it.
  3. Place the yield study and the meter at the same point. If they differ, add a loss factor from the study point to the meter.
  4. Compute billed energy and revenue from that factor, as in the formula below.
  5. Put one-off connection works that the seller pays into the funding requirement. Put recurring grid charges into operating costs, linked to delivered or billed energy as the contract says.
  6. Run DSCR for the loss and the charge, and check the distance to the 1.20x lock-up level in each year.
  7. If the buyer builds the connection, link the earliest delivery date to its completion date and run the delay case.
Revenuet=Tariff×Generationt×(1−loss to the delivery point)\text{Revenue}_t = \text{Tariff} \times \text{Generation}_t \times (1 - \text{loss to the delivery point})

The loss term is zero when the yield study already reports energy at the delivery point. In the example the delivery point is the plant substation, so the study figure of 70.0 GWh is the billed figure.

What are the common mistakes?

Frequently asked questions

Where does title to the power pass in a solar PPA?

In the public contracts that state it, title and risk of loss pass at the delivery point. Contracts differ on where that point is, so the model should read the definition rather than assume it.

Who owns the revenue meter?

Practice varies. One template uses the seller's meter, one has the purchaser own the main meter and the seller a back-up, and a Mexican guide says the buyer normally bears the equipment cost.

What happens if the meter fails or reads wrongly?

One public PPA takes the energy for the affected period from the check meter. If there is no check meter, it sends the quantity to agreement, and then to an expert if the parties cannot agree.

Do the 0.3% and 2% meter figures change the invoice?

In the two templates we opened, they trigger a meter check or a calibration request. They are not tariff adjustments and we do not present them as market norms.

Who pays for line losses?

It depends on the contract. Some put losses before the delivery point on the seller and losses after it on the buyer. Others name a line, such as the line from the delivery point to the interconnection point, and give its losses to the seller.

Does the delivery point change debt sizing?

Yes, through CFADS. In the example, a 1.5% loss and a USD 2.0 per MWh charge together would reduce DSCR-sized debt by about USD 1.3m.

Sources

Pages opened on 5 October 2026. The example project is invented and has no source.