By SolarQuant Editorial. Published 2026-10-05. Last updated 2026-10-05.
Conditions precedent decide when a solar PPA starts to bind and by when the seller must show permits, financing and security. Public templates differ: some make the PPA effective only once conditions are met, others bind on signature and add milestones or termination rights. A modeller treats each condition as a dated test, because in several templates a missed long-stop date ends the revenue contract before financial close.
The example is an invented 40 MWp ground-mounted solar plant in no named market. One buyer takes the power at the plant substation and pays in USD under a 20-year PPA that starts at the commercial operation date. Construction takes 12 months, and senior debt is sized on the lender's P90 case.
Every figure below is invented. Cases that change a clause are shown as separate "what if" cases on this same plant.
| Item | Example figure |
|---|---|
| Plant | 40 MWp, one buyer, delivery at the plant substation |
| PPA term and build | 20 years from commercial operation, 12 months construction |
| Tariff | USD 80 per MWh, flat |
| Year 1 P90 generation | 70.0 GWh |
| Year 1 P90 revenue | USD 5.6m (about USD 0.467m a month) |
| Year 1 CFADS, lender's case | USD 4.2m |
| Senior debt | USD 25.1m over 12 years, 7.0% all-in, DSCR sized at 1.30x |
| Gearing and equity | 62.7% gearing, USD 14.9m equity |
| Lock-up and default DSCR | 1.20x and 1.10x |
| Delay (invented) | Commercial operation 3 months late loses USD 1.4m of year 1 revenue |
| Delay damages (invented) | USD 6,000 a day, capped at 180 days (USD 1.08m) |
Simple models use annual periods. Real deals usually use six-month periods.
Conditions precedent are events or documents that must be in place before a PPA, or some of its terms, becomes effective. The World Bank PPP resource page says: "The PPP contract typically includes completion of (some of) these elements as Conditions Precedent, which must be met for the contract to become effective."
Public templates show three ways of handling the idea.
In each case the modeller needs the same thing: a list of conditions, a date for each, and a rule for what happens if a date is missed.
The conditions fall into a few groups: permits and approvals, financing, land and construction contracts, grid connection, regulator approvals and security. No template lists all of them. The table shows what each public page names, so a modeller can build a checklist and drop what the signed PPA does not contain.
| Condition | What the template says | Template and region |
|---|---|---|
| Permits and approvals | Seller receives "all regulatory and governmental permits, consents and approvals required to construct and operate the Projects" | World Bank standardised synthetic PPA (global template) |
| Permits and approvals | Owner notifies the buyer that all Government Authority approvals have been obtained | PwC solar PPA template (Australia) |
| Permits and approvals | Seller obtains zoning, land use and building permits at its sole cost | SEIA C&I PPA (United States) |
| Debt financing | Seller receives "firm commitments from one or more Finance Parties" for the total debt for construction | World Bank synthetic PPA (global template) |
| Debt financing | Owner notifies the buyer that it has entered into a financing agreement | PwC solar PPA template (Australia) |
| Financial close notice | Purchaser receives notice from AEDB, the agency named in the template, that financial closing has occurred | Standard energy purchase agreement, wind (Pakistan) |
| Land and construction | Land lease for the site and the EPC contract are executed and valid | PwC solar PPA template (Australia) |
| Grid connection | Connection agreement is executed and valid (shown in square brackets, so optional) | PwC solar PPA template (Australia) |
| Grid connection | Interconnection agreement in place by a milestone date | Law firm guide to utility-scale PPAs (United States) |
| Grant funding | Receipt of the named grant funding is notified to the buyer | PwC solar PPA template (Australia) |
| Regulator approval | Seller delivers the benchmark energy table approved in writing by the regulator, only if it elects to revise the table | Standard energy purchase agreement, wind (Pakistan) |
| Regulator approval | Failure of a utility commission to approve the PPA or its cost pass-through is a common early termination ground | Law firm guide to utility-scale PPAs (United States) |
| Security | Seller delivers its letter of credit to the purchaser | Standard energy purchase agreement, wind (Pakistan) |
Our reading, for the example: lenders usually want a signed and effective PPA before first drawdown. The World Bank page says financial close happens only when "all conditions on those agreements have been met". So the model checklist for the 40 MWp plant should carry permits, land, the construction contract, grid connection, financing and the buyer's USD 1.4m letter of credit as dated lines.
In most public templates the seller satisfies the conditions, and the buyer receives proof. Waiver rights differ, and they matter because a waived condition can bring the PPA into force before a lender is ready.
What it changes in the model: the party that satisfies a condition carries the cost of a late date. In the example, if the seller is late on a permit and commercial operation slips by 3 months, the seller loses USD 1.4m of year 1 revenue.
A long-stop date is the last day by which the conditions must be satisfied. After it, the contract falls away or a party may end it. The World Bank page says: "PPP contracts often specify a final date by which the contract terminates, and/or a bid bond is forfeited, if the Conditions Precedent are not met."
The templates differ on how long the period is, who can extend it and who can terminate.
| Template and region | Long-stop | Who can end the contract |
|---|---|---|
| Jordan standard PV PPA | Financial Close Longstop Date: "six (6) months after the signing date", or an extension approved by NEPCO | Agreement is "cancelled" and the parties release each other |
| Pakistan standard energy purchase agreement (wind) | The date required for financial closing in the Letter of Support, as extended by AEDB | The purchaser, by written notice effective on delivery |
| World Bank standardised synthetic PPA (global) | CP Longstop Date, left blank for the parties to fill | Either party, with immediate effect, by written notice |
| PwC solar PPA template (Australia) | Condition Longstop Date, set as a date or a number of days after commencement, or a later date agreed in writing | Either party, by written notice |
| SEIA C&I PPA (United States) | Commencement of installation within a blank number of days after the effective date | The purchaser, on "thirty (30) days' prior written notice", unless the seller starts installation within that notice period |
In the Jordan, Pakistan and World Bank templates the parties are released from further obligations. In the World Bank synthetic PPA, the parties are discharged "without prejudice to any rights, obligations or liabilities that have accrued up to the date of termination".
For the example we use an invented long-stop of nine months after signing. We also assume, as an invented planning case, that conditions are met and financial close happens at month 6. That leaves three months of float before the PPA can be ended.
Financial close moves when a condition moves. The World Bank page defines it: "Financial close occurs when all the project and financing agreements have been signed, all conditions on those agreements have been met, and the private party to the PPP can start drawing down the financing to start work on the project."
The order of events differs by template. In the Jordan standard PV PPA, financial close is itself the long-stop test. In the World Bank synthetic PPA, firm debt commitments are a condition, so they come first. In the Pakistan template, the whole agreement takes effect only after notice of financial closing and delivery of the seller's letter of credit.
In the planning case, conditions are met and financial close falls at month 6, so construction runs to month 18. A slip of 3 months puts financial close on the long-stop itself, with no float left, and operation starts at month 21.
What it changes in the model: our reading is that the build clock starts at financial close, so the slip moves operation by 3 months. In the example that loses USD 1.4m of year 1 revenue. If the PPA also keeps a fixed target date for commercial operation, the seller would owe the invented delay damages of USD 6,000 a day, or USD 0.54m for 90 days. The sibling article "The commercial operation date, longstop dates and delay damages" covers those terms.
Treat conditions precedent as a dated checklist that sets the financial close date, then test the gap to the long-stop. Financial close cannot come before the last condition, and the float is the time left before the PPA can be ended.
A condition precedent must be met before the contract, or part of it, becomes effective. A condition subsequent is checked after the contract is already running. In the PwC template, the agreement runs from signing and may be terminated if the listed conditions are not met by the longstop date.
No. The US law firm guide, the SEIA template and the SECI rooftop template take effect on signing. The Jordan and Pakistan templates bring only some articles into force on signing and the rest later.
Practice varies. The Jordan template gives six months from signing for financial close, with extensions approved by the utility. The World Bank synthetic PPA and the PwC template leave the date blank. The nine month period in our example is invented.
It depends on the template. The World Bank synthetic PPA lets only the buyer waive the seller's permit and financing conditions. The PwC template requires written agreement of both parties.
In the templates we opened, the contract can end or is cancelled. The Jordan template cancels it automatically, while the Pakistan template lets the purchaser terminate by notice. The World Bank synthetic and PwC templates let either party terminate.
Pages opened on 5 October 2026. The example project is invented and has no source.